INES-event
INES 0

Hydrogen Recombiner functional testing not satisfactory

On January 24, 2011 the Laguna Verde NPP Unit 2 was operating at 21% of rated power. While testing the Hydrogen Recombiner System Division I, it was observed that there was not an increment in the temperature of its heater; therefore the test was not satisfactory. All other safety systems were at operative condition.

Location: LAGUNA VERDE-2
Event date: Mon, 24-01-2011
Nuclear event report
Legenda & explanation