Thursday, November 20th, 2008
Nov 17 (Interfax) – The Russian nuclear fuel producer TVEL and Slovenske Elektrarne signed two long- term contracts on the production and delivery of fuel to Slovak nuclear power plants on Monday, an Interfax correspondent reported from the signing ceremony.
Slovenske Elektrarne Director General Paolo Ruzzini and TVEL President Yuri Olenin are signatories to the document. The ceremony took place at the TVEL Machine-Building Plant. (more…)
Posted in Bohunice, Mochovce, Slovenske Elektrarne, TVEL | Comments Off
Wednesday, November 12th, 2008
Projected cost of Mochovce’s completion has ballooned
10 Nov 2008 Beata Balogová Business – JUST weeks after the government approved its strategy on energy security, which is intended to guide policy for the next 20 years or so and which defined nuclear energy as one of its key pillars, Slovakia’s dominant power generator started the construction phase of two further blocks at the Mochovce nuclear plant. (more…)
Posted in Mochovce, Russia, Slovenske Elektrarne, VVER, EIA, Euratom, Financing, Greenpeace | 1 Comment »
Tuesday, November 4th, 2008
MOCHOVCE, Slovakia, Nov 3 (Reuters) – Italy’s utility Enel SpA plans to spend around 90 billion crowns ($3.8 billion) in Slovakia through its 66 percent-owned power generator Slovenske Elektrarne, Chief Executive Fulvio Conti said on Monday.
Conti said the company may reassess other Slovak investment plans worth another 20 billion crowns. (more…)
Posted in ENEL, Mochovce, Slovenske Elektrarne | Comments Off
Tuesday, August 26th, 2008
BRATISLAVA, Aug 25 (Reuters) – Slovak power firm Slovenske Elektrarne (SE) has launched a tender to find a builder to finish two new blocks at the Mochovce nuclear power plant, it said in the Official Journal of the European Union on Monday.
The power generator, managed by Italian utility and 66 percent shareholder Enel, said bidders should submit letters of interest by Sept 18. It said it expected final bids would be due on Dec 8. (more…)
Posted in Bohunice, Mochovce, Slovenske Elektrarne | Comments Off
Wednesday, August 13th, 2008
BRATISLAVA, Aug 12 (Reuters) – Slovakia is worried power generator Slovenske Elektrarne (SE) may be late finishing a second nuclear power plant, a delay which could damage the economy, Prime Minister Robert Fico said in remarks carried by a newspaper on Tuesday.
Fico asked SE, 66-percent owned by Italy’s utility Enel, to present a detailed timetable of work on the two 440 MW blocks at the Mochovce nuclear plant, which should be completed in 2012-2013 at a cost of 1.6 billion euros. (more…)
Posted in Mochovce, Slovenske Elektrarne | Comments Off
Wednesday, July 16th, 2008
Bratislava, 16 July: Russian open joint-stock company TVEL has maintained its position in Slovakia, having won the tender for the supply of nuclear fuel for five power-generating units of the local Mochovce and Bohunice nuclear power plants until 2015, management company Slovenskie Elektrarne has reported.
These plants were built to Russian design and equipped with VVER-440 reactors. (more…)
Posted in Bohunice, Loviisa, Mochovce, Rosatom, Slovenske Elektrarne, TVEL, Uranium, VVER, Westinghouse | Comments Off
Tuesday, July 15th, 2008
BRUSSELS, July 15 (Reuters) – The European Commission recommended on Tuesday that Slovakia improve the safety of two planned new units at its Mochovce nuclear power plant.
“Even though the project shows compliance with current national regulations as well as international recommendations … the Commission recommended a set of additional measures,” Commission spokesman Ferran Tarradellas Espuny told a briefing. (more…)
Posted in Mochovce, European Commission | Comments Off
Tuesday, July 8th, 2008
Journalist Goldirova sent, from Brussels, a report on a letter written by the Slovak prime minister, in which he warned the European Commission that, unless it soon announced its position on the completion of Mochovce [nuclear power station], the Slovak Government would have to “consider all options, including a proposal to postpone the decommissioning of the second block of the V1 reactor [in Jaslovske Bohunice nuclear power station] until 2010.” It follows from the report that Prime Minister Fico now behaves in the same way towards the EU as he behaves in domestic politics. (more…)
Posted in Bohunice, Decommissioning, Mochovce | Comments Off
Tuesday, June 17th, 2008
BRATISLAVA, June 16 (Reuters) – Italy’s utility Enel said on Monday it has boosted the installed capacity at Slovakia’s nuclear power plant Mochovce by seven percent to ease the country’s electricity import needs. Enel, majority owner of leading domestic power firm Slovenske Elektrarne which operates Mochovce, said the capacity boost was to offset the decommissioning of two units at the country’s oldest nuclear power plant at Jaslovske Bohunice. (more…)
Posted in Bohunice, Decommissioning, Mochovce, Slovenske Elektrarne | Comments Off
Thursday, May 29th, 2008
BRATISLAVA (AFP) – Environmental group Greenpeace will lodge a legal challenge to Slovak authorities’ go ahead for the completion of two nuclear power stations in the country’s west, a representative said Wednesday.
The organisation will complain to the supreme court against the go ahead for completion of Mochovce’s third and fourth nuclear reactors without prior environmental impact assessments being carried out. (more…)
Posted in Bohunice, Mochovce, Slovenske Elektrarne | Comments Off